S Korea's Polymirae plans Yeosu PP facility turnaround in Oct-Nov
陈燕
-
0
留言 -
436
浏览
(ICIS news)--South Korea’s Polymirae plans to shut part of its Yeosu polypropylene (PP) facility in October and November for maintenance.
“The No 1 line will be shut from 7 October to 10 November, and the No 2 line will be shut from 17 October to end October,” the source said.
These two lines with a combined capacity of 300,000 tonnes/year resumed production on Monday after a brief outage due to feedstock issues, he said.
“The lines are operating at over 90% now,” he added.
The producer had no maintenance plans for its two other PP lines at Yeosu with a combined capacity of 300,000 tonnes/year this year, he said.
Polymirae决定在10月至11月停车保养其部分丽水PP装置。1号装置从10月7号停车到11月10号,2号装置10月17号到10月底。