Japan’s Asahi Kasei to shut SM unit in Oct for turnaround

陈燕

  • 1

    留言
  • 514

    浏览
Japan's Asahi Kasei Co plans to shut its 390,000 tonne/year No 3 SM unit at Mizushima for a scheduled 40-day turnaround next month.The maintenance would begin from 9 October. Its 320,000 tonne/year No 2 SM unit in the same location, which underwent a 30-day turnaround in February this year, will continue to operate normally during the shutdown of No 3 line. Its smallest 150,000 tonne/year No 1 unit was mothballed in 2007.
2009-09-16 收起回复

陈燕: 日本旭化成将于下月停车其年产39万的3号SM装置进行为期40天的检修,检修从10月9号开始。 该公司年产32万的2号SM装置将在3号装置检修期间正常运转,该装置于今年2月进行了为期30天的检修。 该公司最小的年产15万的1号装置于2007年封存。