Sumitomo Chemical Singapore plans to restart its MMA line no 1 and PMMA line 1 located at Jurong Island around 21 August after a 20 day shutdown.
The MMA line 1 with a capacity of 53,000 tonnes/year and the 50,000 tonne/year PMMA line 1 were shut on 3 August for annual maintenance shutdown, the source said.
Sumitomo had restarted its PMMA line 2 of capacity 50,000 tonne/year in end-May this year after shutting it late last year amid slow regional demand. This line was now operating well.
Sumitomo Chemical operates three methyl methacrylate (MMA) lines with a total capacity of 220,000 tonnes/year at the same site in Singapore. Of the three, the 80,000 tonne/year line no 2 was yet to restart following a shutdown in April 2008 due to technical problems.
Sumitomo operates two PMMA lines with a total capacity of 100,000 tonne/year at this facility.
住友化工(新加坡)计划在8月21日重启MMA1号装置和PMMA1号装置
相关商品帖子
-
张静 2024-11-08
-
13370556116 2024-10-22
-
13805338739 2024-10-10
-
张静 2024-09-29
-
山东信恒化工有限公司销售部张经理 2024-09-13
商品其他帖子
更多
-
信恒化工高经理 2024-10-30
-
济南澳辰化工有限公司 2024-10-17
-
信恒化工高经理 2024-10-17
-
15610169633 2024-05-08
-
济南澳辰化工有限公司 2024-04-25
-
15553101218 2024-04-22
-
15553101303 2024-03-14
-
济南澳辰化工有限公司 2023-11-23