S Korea's SK Energy to restart Ulsan PX No1 by 11 Dec

陈燕

  • 1

    留言
  • 556

    浏览
South Korea’s SK Energy will restart its Ulsan-based paraxylene No1 facility with a capacity of 350,000 tonnes/year on 11 December after a month-long turnaround. Meanwhile, the company’s No2 PX facility at the same site was operating at nearly full capacity. The source said minor maintenance work would be carried out on the two units in the first quarter of 2010 but no dates have been firmed up yet.
2009-11-19 收起回复

陈燕: 韩国SK Energy将于12月11日重启其年产35万的对二甲苯1号装置,该公司的2号装置目前接近全负荷运转。相关人员表示2010年第一季度将对这两台装置进行小型保养,但具体时间还没定。。。

2009-11-19

总条数:1条